Quiz 11
| Question 1 (1 point) |
| Holding all else equal, the profitability index will fall following an increase in the: |
- cost of capital.
- benefit-cost ratio.
- IRR.
- NPV.
|
| Question 2 (1 point) |
| The discount rate that equates present value of cash inflows and outflows is called the: |
- component cost of capital.
- weighted average cost of capital.
- after-tax weighted average cost of capital.
- IRR.
|
| Question 3 (1 point) |
| Acceptance of investment projects where IRR > MCC: |
- will increase the value of the firm.
- will decrease the value of the firm.
- have no impact on the value of the firm.
- none of these.
|
| Question 4 (1 point) |
| Acceptance of new investment projects will increase the value of the firm provided that: |
- IRR > ROE.
- ROE < IRR.
- ROE = IRR.
- none of these.
|
| Question 5 (1 point) |
| The change in net cash flows due to an investment project is called: |
- marginal profit.
- marginal revenue.
- incremental cash flow.
- marginal cash flow.
|
| Question 6 (1 point) |
| An estimate of the firm's cost of equity capital is: |
- the market return on common stocks.
- the market return on common stocks multiplied by beta, the firm's risk index.
- expected dividend yield plus projected growth.
- expected dividend yield.
|
| Question 7 (1 point) |
| The pattern of returns for all potential investment projects is the: |
- investment opportunity schedule.
- marginal cost of capital.
- optimal capital budget.
- optimal capital structure.
|
| Question 8 (1 point) |
| Examples of mandatory nonrevenue-producing investments are provided by: |
- cost reduction projects.
- expansion projects.
- replacement projects.
- safety and environmental projects.
|
| Question 9 (1 point) |
| Net present value is the: |
- current-dollar difference between marginal revenues and marginal costs.
- change in net cash flows due to an investment project.
- change in before-tax cash flows due to an investment project.
- change in net after-tax cash flows due to an investment project.
|
| Question 10 (1 point) |
| When net present value is positive: |
- the internal rate of return equals the cost of capital.
- the internal rate of return exceeds the cost of capital.
- the internal rate of return is less than the cost of capital.
- the internal rate of return equals zero.
|
| Question 11 (1 point) |
| The most difficult step in capital expenditure analysis is estimating: |
- the internal rate of return.
- the cost of capital.
- the cost of investment.
- project cash flows.
|
| Question 12 (1 point) |
| Cash flows include depreciation: |
- to account for taxes effects.
- as a cash expense.
- if accelerated depreciation is chosen.
- to reduce projected cash flows.
|
| Question 13 (1 point) |
| Firms should finance a project if its: |
- expected cash flow is positive.
- net cash flow is positive.
- internal rate of return is positive.
- net present value is positive.
|
| Question 14 (1 point) |
| A firm must choose between two projects, X and Y. Project X has the highest net present value, but project Y has the highest profitability index. The firm should choose project Y if: |
- the firm is a risk seeker.
- the firm is risk averse.
- the firm has substantial investment resources.
- the firm has limited investment resources.
|
| Question 15 (1 point) |
| If the tax rate is 25% and the prevailing interest rate is 12%, the after tax cost of debt is: |
- 3%.
- 9%.
- 16%.
- 37%.
|
| Question 16 (1 point) |
| The crossover discount rate only equates the: |
- NPV for two or more investments.
- IRR for two or more investments.
- present value payback period for two or more investments.
- all of these.
|
| Question 17 (1 point) |
| When NPV is positive, the IRR: |
- is less than the cost of capital.
- equals the cost of capital.
- exceeds the cost of capital.
- none of these.
|
| Question 18 (1 point) |
| The risk-free rate of return is the investor reward for: |
- risk-taking.
- postponing consumption.
- relative stock-price variability.
- absolute stock-price variability.
|
| Question 19 (1 point) |
| The cost of capital is the: |
- component cost of debt.
- component cost of equity.
- both A and B.
- discount rate.
|
| Question 20 (1 point) |
| The beta coefficient is: |
- a relative measure of stock-price variability.
- an absolute measure of stock-price variability.
- equal to the standard deviation divided by covariance.
- none of these.
|
Copyright 2008,
by the Contributing Authors.
Cite/attribute Resource.
admin. (2009, January 27). Quiz 11. Retrieved November 23, 2009, from Free Online Course Materials — USU OpenCourseWare Web site: http://ocw.usu.edu/economics/managerial-economics/quiz11.htm.
This work is licensed under a
Creative Commons License.